FieldWise Calculator

Sand and Cement Calculator

Estimate the cement and sand for mortar, screed or render, or the cement, sand and gravel for a concrete pour. Pick a mix ratio, enter the area and depth, and get bags of cement plus sand and gravel in cubic feet and tons. Figures use a standard dry-volume factor and typical material weights, so treat them as a planning estimate.

Finished volume...
Dry materials needed...
Cement (94 lb bags)...
Sand...
Sand weight...

Understanding the inputs

ratio
The mix ratio by volume, cement first. 1:3 is a rich mix, 1:6 is weaker and goes further. For concrete the three numbers are cement, sand and gravel, so 1:2:4 is one part cement, two parts sand, four parts gravel.
area
The surface area you are covering, in square feet. Length times width.
length
The longer side of the pour, in feet.
width
The shorter side of the pour, in feet.
depth
The thickness of the layer, in inches. Floor screeds are often 2 to 3 inches and slabs 4 inches or more. Check what your project needs.

Common mix ratios (by volume) and where they are typically used

MixTypical useCement bags per cubic yard of wet mix
Mortar 1:3Rich bedding mortar and floor screedAbout 10.4
Mortar 1:4General bricklaying, screed and renderAbout 8.3
Mortar 1:6Weaker, lighter-duty mortarAbout 5.9
Concrete 1:1.5:3Stronger concrete for heavier loadsAbout 7.6
Concrete 1:2:4General purpose concrete, paths and slabsAbout 5.9
Concrete 1:3:6Lean mix for fill and non-structural useAbout 4.2

Frequently asked questions

How do I calculate sand and cement for a mix?

Work out the wet volume (area times depth), multiply by 1.54 to get the dry volume of materials needed, then split it by the ratio. For 100 sq ft at 2 inches deep with a 1:4 mix: 16.67 cubic feet wet, 25.67 dry, so 5.13 cubic feet of cement (6 bags of about 1 cubic foot each) and 20.53 cubic feet of sand.

How much sand and cement do I need for a 1:4 mix?

A 1:4 mix is one part cement to four parts sand, so cement is one fifth of the dry volume and sand is four fifths. Per cubic yard of wet mortar that is roughly 8.3 bags of cement and 33.3 cubic feet of sand. Use the mortar tab to scale it to your own area and depth.

What is the dry-volume factor of 1.54?

When cement, sand and water are mixed, the grains pack together and the wet mix takes up less space than the loose dry materials. A common rule is to start with about 1.54 times the finished volume in dry materials. Real mixes vary with the sand grading and moisture, so many people round up slightly.

How much does a sand and cement mix weigh?

This calculator assumes dry sand weighs about 100 pounds per cubic foot, so 20.53 cubic feet of sand is roughly 1.03 tons. Damp sand is usually heavier. A 94 lb bag of Portland cement is treated as about 1 cubic foot. These are rough values, so check your supplier for the exact bulk density.

What ratio should I use for concrete?

A 1:2:4 mix (cement, sand, gravel) is a common general purpose choice, 1:1.5:3 is richer and stronger, and 1:3:6 is a lean mix for fill or blinding. For a 10 ft by 10 ft slab 4 inches thick at 1:2:4, you need about 33.3 cubic feet of concrete, which comes to about 8 bags of cement, 14.7 cubic feet of sand and 29.3 cubic feet of gravel. For ready-mix bags, use the concrete calculator.

Is Type 1 the same as a sand and cement mix?

No. Type 1, often searched as "type one calculator", is a UK name for a crushed stone sub-base used under paving and slabs. It is compacted as a base layer and contains no cement. If you need to work out how much sub-base stone to order, use our gravel calculator.

Related calculators